Scheduling a Policy
1. Locate the newly deployed policy in the list under the section POLICY LIST. Click triple dots on the right and select 'Edit & Schedule' to open the policy editor:
![](../__attachments/1174831115/edit%20and%20schedule%20the%20policy.png?inst-v=2f95fef9-6b33-409d-abd7-1c46cd1ff6c9)
2. Open the tab 'Settings' in the upper panel. Select the preferable frequency in the drop-down list. The settings will be saved automatically.
![](../__attachments/1174831115/schedule%20policy%20in%20editor.png?inst-v=2f95fef9-6b33-409d-abd7-1c46cd1ff6c9)
The policies that will potentially create a lot of violations should be run less frequently.
To schedule several policies at a time, check the boxes near the policies in question. Click Schedule Selected (1) that appears above, select the preferable frequency(2) and click Save Selected(3):
![](../__attachments/1174831115/mass%20check%20to%20schedule.png?inst-v=2f95fef9-6b33-409d-abd7-1c46cd1ff6c9)